Today, Keita and Oli turned up the power to the fiber again so we are getting about 30 mW out. This is enough power that you can see the beam transmit the input coupler of the OMCs easily on a card. With the room lights dim, you can see flashing of the beam at both DCPDs with a card. Using the IR sensitive camera, we are able to fine tune the input alignment further.
The beam has been well-aligned to OMCA, and the flashing present at the DCPDs looks mostly like mode mismatch, which makes sense because we made no effort to mode-match our input beam to the OMCs.
The beam alignment to OMCB still needs some work. It looks predominantly like a yaw misalignment, so we need to make some finer adjustments of the upstream optics.
Since all of the BHSS optics have been pre-angled using the clocking tool, I followed the map on slide 86 of T2100190 to place the lenses, mirrors and beam dumps. Just by eye, I can tell we will need to fine tune this alignment further once we have laser beam. I was unable to place one beam dump because it goes roughly where we are pooling the OMCA cables. Once we can route and clamp those cables properly, there will be room for the dump. I haven't placed the QPDs yet, they are still bagged. I also placed the three head optics randomly, since they can't be placed until the OMC iris template is removed.
As a reminder, the order of operations here is to use the iris alignment template to get good input alignment to both OMCs. Then, this template is removed so we can use other precision templates to align the three optics that go at the head of the manta ray: mirrors A/B-R1 and 36-R1. Then, we can finish the rest of the beam paths to the OMC QPDs.
I took a phone video of OMCA flashing and managed to screengrab these two photos from the videos: DCPDA, DCPDB
I returned to the slider positions where we had good green and IR flashes in the filter cavity from Wed 89629. Since this time of good flashes the H:M2 pico was reverted to 0 (it's setting during in chamber work), so the green flashes weren't as high as they were on Wed. Screenshot attached here. In this alignment I went to SQZT7 and looked at the green reflection, it looks like an oval but is coming to the persicope. (photo)
While at the table, I moved the picomotor for H:M2 X to -710, which is where Tony and I had put it 89596 and where we had both IR and green flashes good. I could see the beam move on SQZT7, but it wasn't a big move, and after pico'ing it looks like we still have an oval beam making it to the table.. (photo, screenshot) On the cameras we can clearly see cavity flashes in green but the IR flashes were off the camera, so I went to FCES and centered the flashes on the IR camera (using the seed). I also went back to sqzt7 and aligned the FC green refl onto the diode.
While I was there, I watched the green beam on a card while I moved suspensions to see how much freedom we have to move the suspensions and still get the green beam out of the viewport. I could move ZM1,2,3 and FC1 by a couple hundred urad in both pitch and yaw (although not in either direction), so there is a reasonable adjustment range. Moving these didn't impact the oblong shape of teh beam, so it doesn't seem like that is caused by clipping. I then moved the ZM2 psams settings, and saw a big change in beam shape, it became more round looking on a card for strain guages of 4.15 or 5.15 (our usual setting is 3.15).
I left the alignment back at the one that gave good flashes for IR and green (up to 10, is off in pitch), and with the CLF IR flashes are max 0.15 counts.
TITLE: 03/27 Day Shift: 1430-2330 UTC (0730-1630 PST), all times posted in UTC
STATE of H1: Planned Engineering
INCOMING OPERATOR: None
SHIFT SUMMARY: The +/- Y doors were taken off HAM1 this afternoon alog89672, See Jims' alog89673 for the current CS seismic configuration. I'm not sure if the intercom is working, I didn't hear myself after plugging it in and trying the offices. THe LVEA is now is LASER HAZARD, as is the optics lab.
LOG:
| Start Time | System | Name | Location | Lazer_Haz | Task | Time End |
|---|---|---|---|---|---|---|
| 14:28 | FAC | Kim, Nellie | LVEA | N | Tech clean, Nellie out @ 15:12 | 15:19 |
| 14:58 | FAC | Randy | LVEA | N | Prep for door removal | 15:26 |
| 15:51 | VAC | Travis | LVEA | N | Check HAM1 purge air | 15:57 |
| 16:05 | FAC | Mitch | LVEA | N | Cleanup in the Wbay | 16:22 |
| 16:07 | EE | Fil, Marc | LVEA | N | Cable pulling for moving electronics, HAM3/BSC2 | 17:09 |
| 16:22 | VAC | Nellie | LVEA | N | Tech clean | 17:11 |
| 16:36 | VAC | Gerardo, Randy | LVEA | N | HAM1 door removal! Travis to join | 18:33 |
| 16:41 | FAC | Jason | Optics lab, LVEA | LOCAL/N | Property hunt | 17:21 |
| 16:50 | VAC | Betsy, Mitch, Travis | LVEA | N | HAM1 doors, Mitch Betsy out 1700 | 18:30 |
| 16:51 | FAC | Kim | LVEA | N | Tech clean | 17:44 |
| 17:02 | SEI | Jeff, Sina | Optics lab | LOCAL | SPI work | 18:07 |
| 17:03 | BHD | Oli | Optics lab | LOCAL | BHSS work, magnet pol checks | 20:16 |
| 17:12 | EE | Fil, Marc | MidY | N | Cable search | 19:53 |
| 17:32 | OPS | Ibrahim | Optics lab | N | Put away parts before curtains | 17:46 |
| 17:35 | FAC | Jason | PCAL lab | N | Property inventory | 17:39 |
| 17:38 | OPS | Betsy, Jim | LVEA | N | Cleanroom move by HAM1, Betsy out 1746 | 18:43 |
| 17:53 | EE | Thomas | Vac Prep | LOCAL | In-Vac cables | 19:19 |
| 18:32 | SUS | Ibrahim | Vac-Prep | LOCAL | Joining Thomas | 19:19 |
| 18:55 | BHD | Elenna, Keita | Optics lab | LOCAL | BHSS, Keita out 19:37 | 20:16 |
| 19:20 | SEI | Jim, Betsy | LVEA | N | LOCK HAM1 ISI | 20:07 |
| 19:43 | FAC | Randy | LVEA | N -> Y | Work on emod, handrails | 22:46 |
| 19:49 | SPI | Jeff, Sina, Jason | Optics lab/PSL encl | LOCAL | Measure fiber power, in lab checks then PSL enc checks, Jason out of PSL at 20:40 | 21:25 |
| 19:53 | EE | Fil, Marc | LVEA | N ->Y | Cables, all around HAM3 and BSC2 | 23:10 |
| 19:56 | SQZ | Sheila | LVEA | LOCAL | turn on SQZ laser, potential transition to hazard at SQZT7 | 20:06 |
| 20:11 | EE | Ibrahim, Thomas | Vac Prep | N | In-Vac cabling | 20:18 |
| 20:37 | EE | Ibrahim, Thomas, Sophie | Vac Prep | N | In-Vac cable making, Ibrahim 23:15 | Ongoing |
| 20:20 | ISC | Betsy | LVEA | N | Look into putting tables back | 21:39 |
| 20:48 | ISC | Sheila | LVEA | N | Talk to Fil and Marc, Turn on SQZ laser | 21:03 |
| 21:02 | TCS | Sophie | Vac prep | N | CHETA work | 22:56 |
| 21:22 | ISC | Betsy | Optics lab then LVEA | N | Parts/tools checks then LVEA | 21:56 |
| 21:22 | VAC | Travis, Bram | LVEA | N | Look at laser stop buttons | 21:27 |
| 21:24 | BHD | Elenna | Optics lab | LOCAL | Turn on the laser, cont BHD work | Ongoing |
| 21:31 | OPS | Sheila | LVEA | N -> Y | Laser Hazard transition | 21:47 |
| 21:58 | SQZ | Sheila | LVEA | Y | SQZT7 work, alignment | 22:15 |
| 21:59 | OPS | Jenne | LVEA | Y | Look for Fil/Marc | 22:14 |
| 22:06 | ISC | Keita, Jennie, Betsy | LVEA | Y | HAM1 work | Ongoing |
| 22:08 | SEI | Jeff | LVEA | N | Find part | 22:28 |
| 22:09 | ISC | Jason | LVEA | Y | Join HAM1 team | 22:21 |
| 22:38 | SQZ | Sheila | LVEA then FCES | Y | SQZT7 check before FCES | 23:06 |
| 23:21 | SQZ | Sheila | LVEA | Y | SQZ7 checks | Ongoing |
| 23:29 | SEI | Jim | LVEA | Y | Unlock HAM3 HEPI | Ongoing |
Closes FAMIS39757
Laser Status:
NPRO output power is 1.83W
AMP1 output power is 70.39W
AMP2 output power is 138.8W
NPRO watchdog is GREEN
AMP1 watchdog is GREEN
AMP2 watchdog is GREEN
PDWD watchdog is GREEN
PMC:
It has been locked 20 days, 23 hr 13 minutes
Reflected power = 26.87W
Transmitted power = 104.4W
PowerSum = 131.3W
FSS:
It has been locked for 0 days 2 hr and 21 min
TPD[V] = 0.4974V
ISS:
The diffracted power is around 3.9%
Last saturation event was 0 days 2 hours and 25 minutes ago
Possible Issues:
PMC reflected power is high
Closes FAMIS39341
As expected from the vent and HEPI's being locked on HAMs 1,2,3 and BSC 2,3 the plots look noisier. I don't see any glaring issues with the other chambers.
[Jenne, DaveB, RyanC, Jason, Betsy, Jennie, Keita, Fil, Marc]
Several folks prepping to align optics for HAM1 work noticed at about the same time that several HAM1 and HAM2 suspensions were not behaving as expected. Eg, I tried misaligning and aligning PR3, but nothing happened (I did this because the sliders hadn't changed, but the OSEM readbacks had changed). The team prepping to go into chamber similarly noticed that there were no counts going out to the IOP models.
Fil and Marc had a quick look at the sat amps for the HAM2 suspensions (just in case, even though no one had been near them), and everything looked fine.
Upon going back to the control room, I finally noticed on the CDS overview screen that IOPSUSH12 had its DAC Kill light illuminated. After some clicking around, we found the dac kill watchdog screen, and hit RESET. However, PM1's RMS was still larger than threshold, because HAM1 is at air and the purge air is on, so its undamped motion was too high. I clicked BYPASS on PM1, which let signal go through to damp PM1. PM1 quieted down, and I un-bypassed it by hitting RESET again.
At this point, it seems like all of the suspensions on HAMs 1 and 2 are again behaving as expected.
Rahul, RyanC
Over the past few weeks we've prepped the two basic HXDS assembly (structure sn 035, alog88828 - OMA3 with B2-03 optic, and structure sn 029, alog87998 - OMA2 with A1-03 optic) that we received from LLO. Rahul and Camille assembled these PSAMs at CIT. We attached the wires using the provided HDS Bottom Mass Wire Plate ASSY D2000395 setting the top blade height first using the blade height gauge then feeding the wire down, and the bottom mass (PSAM) with its fixture assembly plate. The wire clamps really wanted to clock when I was doing the final turn, turn and a half on their fasteners so I had to tighten them very slowly. For OMA2 we had some trouble trying to remove the intermediate mass fixture plate D2000230 to replace it with the BOSEM Cam Adj Mtg ASSY as there was a stuck dowel pin. The fixture plate was a V1 version which did not have the emergency release feature that the later version has. We brute forced it out without damaging any components or wires but the intermediate mass shifted a decent amount despite my efforts to keep it still. OMA3 did not have this issue as it was as the V2 plate.
Once we had OMA2 fully assembled, we balanced it then brought it over to the test stand and connected the four OSEMs to the top stage. This first suite of phase 1a measurements was done without the M2 PSAMs cable connected.
The OLV counts were as follows (we later swapped LR and UR, which is reflected below) for OMA2:
UL: 28460 UR: 31900
LL: 29720 LR: 30860
The data/templates live in: /ligo/svncommon/SusSVN/sus/trunk/HXDS/X1/OMA2/SAGM1/Data
and the result pdfs are in: /ligo/svncommon/SusSVN/sus/trunk/HXDS/X1/OMA2/SAGM1/Results
I ran 3 sets of measurements on Wed with a bw of 0.02. The first measurement 2026-03-25_1730 showed some weirdness with LR and lots of cross coupling from Length into Pitch and a bit into Yaw, the shapes were a little different, as well along with the magnitude but that's probably from the coil driver gain. Rahul then swapped the LR and UR OSEMs and double checked the centering, and I ran another measurement 2026-03-25_1900, which looked about the same. Rahul then went and improved the balancing as best he could (the masses were pitching a bit) and I ran a final measurement 2026-03-25_2130.
Overall the Transfer Functions look ok but there's still room for improvement.
On Thursday Rahul balanced and set up OMA3 on the test stand. Unfortunately while manipulating OMA2 one of the bottom M2 stage wires broke, so we will have to replace it and remeasure it next week.
The OLV counts were as follows for OMA3:
UL: 27030 UR: 32100
LL: 27500 LR: 28900
The data/templates live in: /ligo/svncommon/SusSVN/sus/trunk/HXDS/X1/OMA3/SAGM1/Data
and the result pdfs are in: /ligo/svncommon/SusSVN/sus/trunk/HXDS/X1/OMA3/SAGM1/Results
This set of transfer functions, 2026-03-26_1900 also looks ok and similar to OMA2, see the comparison plot of OMA2 and OMA3. Both measurements shows some weirdness with LR that is not seen in an OSEM noise spectra that we're still looking into.
The next steps are to repair the bottom wire on OMA2, attach PSAMs cables, remeasure then fine tune both OMA2 and OMA3.
Tagging EPO for Corey for the pictures. I'm realizing I only have pictures of OMA3, I might comment with more photos on Monday of OMA2.
(Travis, Randy, Fil, Betsy, Marc, Jim, Gerardo)
Both doors for HAM1 are off, +Y and -Y.
- Y Door we had one of the O-rings get stuck to the door, used the tool to set the O-ring back into its groove without a problem. No further issues.
+ Y door, we took a peek at the O-rings and they looked suspiciously good all over, even with a small gap, but then out of the sudden one of the O-rings jumped out and dropped to the floor. So, the +Y door has the flange protectors over a single O-ring.
Purge air was turned up. A photo of the dew point is attached, this as measured this morning by Travis.
A big "thank you" for those that helped with the cleanroom moves.
As of right now, HAM1-2-3 and BSC 2 & 3 HEPI are locked, and after doors came off HAM1 ISI is also locked. HEPIs are all bypassed in the model (by setting ISO master gain to 0). HAM1 should just be left tripped for the work in that chamber, HAM 2 &3 and the BSCs should be left with damping loops engaged, unless there is a need for better alignment to the IFO.
Writing this alog to clarify some mistakes we have made regarding the naming of DCPDs. Jeff clarified to us on call this morning that the naming convention is A- photodiode on reflection, B- photodiode on transmission.
Therefore, here is the now corrected information about which high QE photodiodes are installed where, along with cabling and pin numbers:
OMCA (SN 103)
OMCB (SN 105)
Fri Mar 27 10:10:14 2026 INFO: Fill completed in 10min 10secs
I've added a "degraded state" indicator to the VACSTAT block on the CDS Overview MEDM (magenta oval in attachment). This circle is either the same light green as the block colour, or is a darker green to show at least one gauge has been disabled.
Currently we are running with HAM1 PT100 disabled in VACSTAT due to the vent.
The VACSTAT detailed MEDM (snippet in lower part of attachment) has a "NUM_GAUGES_DISABLED" line added, which turns RED if non-zero.
TITLE: 03/27 Day Shift: 1430-2330 UTC (0730-1630 PST), all times posted in UTC
STATE of H1: Planned Engineering
OUTGOING OPERATOR: None
CURRENT ENVIRONMENT:
SEI_ENV state: CALM
Wind: 4mph Gusts, 1mph 3min avg
Primary useism: 0.03 μm/s
Secondary useism: 0.27 μm/s
QUICK SUMMARY:
Since yesterday, we have received an answer from Ali and Keita, that the determination is that the cathode and anode pins are in the correct location. There is a longer explanation about what's going on here and which diagrams are wrong, but I will leave that to them. Therefore, the only cable work that needs to be done is to adjust the pins on our "bad" cable, and then switch the DCPD cables between OMCA and OMCB.
Morning (no cable work):
Oli and I pulled the first contact that we left from yesterday. We just need one 50/50 45 deg AOI mirror for BHSS, and we were able to completely clean two of this type. More of these mirrors will be needed for the greater BHD layout, so Oli and I need to revisit the other three that still are not clean. For now, they are stored on the flow bench in clean single cases.
We went to begin the BHSS alignment, and found that no laser beam was coming out of the fiber. Some time between this alog, when Camilla and Oli aligned the beam into the fiber, and now, the beam was misaligned again. We think one of the mirrors to the fiber coupler was bumped. Correcting this took a little while. Oli had to leave, so Keita and I continued with the alignment. Luckily, our downstream alignment is still good- with the iris alignment template placed on the BHSS, we can see the beam comes down the center of both irises to OMCA.
Most of the beam reflects off the OMC, so Keita and I started turning up the power into the fiber. At some point, we turned up to 20 mW coming out of the fiber. We could see a faint beam transmit from the input coupler and make it to the output coupler. However, we still had a hard time seeing any beam make it to the DCPDs, probably because the power is still very low. We set up a beam block of the OMC REFL path for now, since it just goes right back off the suspension. At this point, we realized it's probably not a good idea to put so much power into the fiber, so we lowered the power again to have about 2 mW coming out of the fiber.
Afternoon (cable work):
Keita and I proceeded to fix the cables. We first checked which cables went to which pins:
Cable D2300119 (for OMCB): longer is on trans PD, goes to pins 4/5, shorter on refl PD, goes to pins 1/2
Cable D2300118 (for OMCA): longer is on trans PD, goes to pins 1/2, shorter is on refl PD, goes to pins 4/5
We confirmed that this is the correct wiring according to D2200276
Keita opened up cable D2300119, as this is the cable with incorrect wiring- case was wired to pin 2 and pin 5 instead of pin 6 and 9
We confirmed that the cathode is correctly wired to pins 1 and 4, so we only needed to swap 2/6 and 5/9.
Keita proceeded to switch the pins (this is a very short sentence to describe a long and painful process of removing various peek parts, poking pins through holes and resetting all the peek parts once finished)
Keita reclamped the lower part of the wires and we decided that we should clamp it very tight, as there were no gaps in the clamp on the other cable.
We then swapped the cables, as 118 was incorrectly placed on OMCB and 119 on OMCA. We decided to unscrew the PCB assembly on the back of each tombstone, and then swapped cables, paying attention to which cable went to trans and refl. Note: plugging the PCB assembly back into the DCPD pins is much much easier than inserting the DCPDs from the front.
We then decided to confirm the wiring was correct so we:
- checked that the case of each PD was wired to pins 6 and 9 (pass)
- checked the diode polarity was correct betweens pins1/2 and 4/5 (pass)
- checked that there were no shorts between any of the pins in the cable (failed for cable 119)
We found a short between pin 3 and 9 on cable 119. We removed the PCB assembly from the back of the DCPD tombstone and checked again, still a short. Keita then removed the lower part of the dsub9 assembly where the wires are clamped, and there was no longer a short between pin 3 and 9. We found one wire that was a bit stripped (see photo), but this was the wire for pin 4, so that didn't explain the problem. We were not able to find anything that could cause short between pin 3 and 9. We decided that maybe the pressure of the clamp caused this problem, so Keita reclamped the wires but less tightly, no more short. We checked one more time for case wiring, polarity, and shorts and all tests passed. Done!
I took some photos of the BHSS before we started work. Here are a few to show the progress so far. OMCA was uncovered before the photo, OMCB still covered by the butterdish. All the optics in the center are randomly attached. Platform is still locked down. Tagging EPO.
On Monday, Randy, Jordan and the FAC team craned the HAM3 cleanroom over into the appropriate place for HAM3 entrance for installation planned next week. The cleanroom is now up against the BSC2 Platform. As well, Kim and Nellie have been cleaning the HAM3 cleanroom. On Tuesday, Randy craned into place and attached the new Installation Platform Sections G and F to the BSC2 platform. Handrails will be installed next. These platforms allow access from the eMod cleanroom to the BSC2 cross flow Dome cleanroom and platform, as well as provide added walking space between BSC2 and BSC3. They also form 2 sides of the BSC3 platform which will be needed in subsequent vents. Recall, this new LHO BSC2 Installation setup is part of the readiness review for install at https://dcc.ligo.org/E2400329-v1, and is part of a bigger plan to add sections around BSC3 and BSC1 to make a larger platform instead of moving them and encountering interferences other items like racks, trays and equipment.
Tagging for EPO photos.
"It is a truth universally acknowledged, that a single man in possession of a good fortune, must be in want of a wife"
- Jane Austen, opening line of Pride and Prejudice
But unfortunately for both us and them, sometimes those men are winged termites in the Optics Lab.
As Elenna and I were cleaning up our work in the back optics table this afternoon, we noticed a few winged termites, and ended up finding maybe almost 10 in total walking around on the floor in the back area of the optics lab near the wall mounted cabinets between the two cleanrooms. We got rid of them but couldn't find where they had come from. I'm wondering if they're maybe coming from an opening under one of those cabinets? Last year this happened but those came out from under the flow benches along the wall - not sure if this is part of that same colony that survived or a different colony.
Yesterday (Mar 26), as we cleaned up after BHSS work, I looked around for more termites. I found only one in the corner of the lab near a circle of power cables, just underneath where we hang BNCs and other cables. It appeared to be dead. Not sure if it's new or I missed it the day before.
Sheila, Camilla.
We decided to pause on looking for the FC alignment and look at SQZ alignment into the IFO. To check our irises and possibly look for scattering shelves.
Locked SEED_DITHER with 75mW into fiber. Moved ZM3 to get OPO_IR PD up to max 0.9mW. Opened BeamDiv and after aligning SRM, mis-aligning SR2, could see beams on AS_A,B and C. AS_A and B had a similar size ~60 to reported before (e.g. 86965), but there was less power on AS_C: 4e-4 rather than the previous 7e-4.
We used Ryan's DRMI time from 89573 to put OM1, OM2 and SRM back. The with the SQZ SEED injected, we tried to use SQZ centering loops to center on AS_A and AS_B, this didn't work quite as expected. ZM4 kept saturating although these loops had worked Janaury 19th, before moves were done on the VOPO to help with clipping e.g. 88966.
Then went back to alignment on Jan 31st with 88976 with ZM1,2,3, 4,5,6 FC1. And took OM1,2,SRM to the January 19th positions. However here we saw no light on SQZT7 OPO IR PD, HAM7 WFs or in HAM6 on the AS_A,B,C diodes. This was done at 23:10 UTC. Comparisons of osems attached. The sliders to get these osems values are fairly different, see attached, so I also tried going to these slider values, that gave me some light on SQZT7 IR PD, HAM7 WFS and FCES with SEED injected, see attached. HAM6 AS diodes saw nothing.
Sophie, Camilla
This morning, starting from this vented slider alignments, I randomly moved ZM1 until we had IR and green light on the FCES PDs. I misaligned FC1 and FC2 to single pass light. Then I could move ZM3 in pitch from P,Y (-324,-200) to (-506, -200) to get max light on IR FCES PD. In both these positions, we get scattered light on the camera and light on both IR and green PDs. This makes me think the best position in pit h is in the middle of these, ZM3 (-415, 200). We tried to repeat this excise in yaw but only could get the one edge. Even after movingZM1 in YAW in both directions, I couldn't find the other side of the yaw clipped beam. Attached is the sliders when we thought we were centered in pitches and clipping the coating on one side in yaw.
We need 4 things for the squeezer to operate:
Continuing from where Sophie and Camilla left off, I confirmed that the green I see on the FCES green camera is a single pass beam by misaligning both FC1 and FC2, they do not move this beam, and also confirmed that it's green by toggling the fiber input. I moved ZM3 to bring this to center on the camera, as we have not disturbed this FCES green path since O4. Then I did a raster on FC1 to get the IR seed reflected onto the SQZT7 IR PD (screenshot).
After moving FC2, I could see some green and IR on the FCES cameras. For IR, this is not the single pass beam but some reflections off FC1, for green we still see the single pass beam and a second beam coming close to the single pass beam, but it seems to have a very different beam size. screenshot. After this I went to SQZT7 and saw that the FCGS refl beam is making it to the table and aligned it onto the diode. Now we have 2.5 of the 4 things we need for the squeezer to work: green on SQZT7, IR on SQZT7, and the green single pass is heading towards FC2 well, which is part of what we need to get green flashes.
Sophie and I went to FCES. We tried moving FC2 to see what happened on the green transmission, we can see the beam reflected off FC2 leaks around the edge of the FC2 coating for some alignments, but that we can overlap them for some alignments, but do not see cavity flashes.
Camilla moved ZM3 back to the alignment where she found the green centered between the two places where it goes over the edge of the coating. This was a simlar situation in green.
In IR, we did see a single pass beam on the camera when Camilla steered ZM3. In 986 ZM3 is in the position where Camilla thinks IR is centered on FC2, you can see two green spots, and to the right and slightly below a very faint IR beam (I had to clean the laptop screen, turn the brigthness up to see it). In 988 ZM3 was at -506 P, -200 Y, the negative pitch clipping, you can see the brighter IR beam where it is transmitting through the uncoated part of FC2. 990 is ZM3 -324 P, -200 Y, going over the lower edge of the coating. 994 is with FC1 + FC2 in the aligned guardian state, moving FC2 until we saw something on the IR camera. 996 is for FC2 359 P, 28 Y, there was light on the IR diode, but the photo is dark.
We previously reported that the wiring to ground on the OMCA DCPD dsub9 cables seemed odd, see 89562. There appears to be two conflicting diagrams of the pin wiring, D2200276 and D2300119. Neither of these diagrams follow the correct pin naming practice either.
Today, Oli and I checked the ground connectivity for the OMCB DCPD dsub9. The case ground is wired to what is labeled pins 6 and 9, according to both of the diagrams above and also proper convention. However, this is different from OMCA, where the case ground is wired to pins 2 and 5 (following the incorrect naming of the diagrams above), or pins 1 and 4 (following correct naming conventions).
So either way, we have two different wiring set ups for OMCA and OMCB. We have only checked the ground pins so far, and it seems like we should confirm the cathode and anode wiring as well.
To summarize:
- we have two different diagrams for pin wiring
- OMCA and OMCB are wired differently from each other
- the diagrams are not following proper pin naming convention which is making this more confusing
Two problems with the drawings.
1. Case grounding.
As for cable and connection drawings, D2200276-v4 wiring diagram specifies that pin1-2 and pin4-5 twisted pairs carry the photocurrent, pin1 and pin4 being cathode, and case grounds are routed to pin6 and pin9, between DCPDs and the in-vac DCPD frontend. See the 1st attachment.
D2300118 DCPD to DB9M cable doesn't agree with the wiring diagram, it routs the case grounds to pin 2 and pin 5. See the 2nd attachment.
D1300369 DB9F-DB9F cable drawing agrees with the wiring diagram in that pin1-2 and pin4-5 are twisted pairs.
D2000592-v3 in-vac DCPD frontend seems to be compatible with the wiring diagram in that it routs the pin6 and 9 to the ground.
So, D2300118 DCPD to DB9M cable drawing is singularly incompatible with others.
Below is a summary table of the above together with reality check of the DCPD-DB9m cable. It seems that there's no way OMCA cable works. Anode/Cathode check wasn't performed (yet).
| pin1 | pin2 | pin6 | pin4 | pin5 | pin9 | |
| D2200276-v4 wiring diagram | Cathode1 | Anode1 | Case1 | Cathode2 | Anode2 | Case2 |
| D2300118 DCPD to DB9M cable | Cathode1 | Case1 | Anode1 | Cathode2 | Case2 | Anode2 |
| D1300369 DB9F-DB9F cable (pass through) | compatible with the wiring diagram in that pin1-2 and pin4-5 are twisted pairs. | |||||
| D2000592-v3 in-vac DCPD frontend (outside of the enclosure feedthrough) |
Internally routed to PD1 pin1 |
Internally routed to PD1 pin2 |
Internally routed to GND |
Internally routed to PD2 pin1 |
Internally routed to PD2 pin2 |
Internally routed to GND |
| OMCA reality | Case | ? | ? | Case | ? | ? |
| OMCB reality | ? | ? | Case | ? | ? | Case |
2. Polarity of the diode seems to be wrong.
Assuming that the wiring diagram and the in-vac DCPD frontend circuit diagram are both correct, cathode1 and anode1 are routed to "PD1 pin1" and "PD1 pin2" while cathode2 and anode2 are routed to "PD2 pin1" and "PD2 pin2". So, pin1 and pin2 inside the frontend chassis are cathode and anode. Again look at the first attachment.
However, whey you look at the circuit diagram of the frontend (3rd attachment), pin2 is connected to the positive bias and pin1 is grounded (via the huge inductor). This means that the PD is forward-biased and will be unusable. Is this only in the drawings?
What to do.
First thing is to check the diode polarity in reality, i.e. if cathode is routed to pin 1 and 4 (which I expect) or to pin 2 and 5 (which I don't expect). In parallel, check with Ali/Dean that my assessment of the polarity makes sense or not.
Depending on the results of the polarity investigation, we'll determine which cable needs to be reterminated how. If we're lucky we'll just reterminate only one cable, but if the PD polarity is indeed wrong we'll have to reterminate all cables.
Here is a further update. This is based on conversations with Keita and Betsy, and emails to and from CIT and LLO.
At first, it appears one issue here is that I have made a mistake OMC placement, as D2200276 indicates that OMCB should have the DCPD cable labeled D2300119 (and PZT cable D2300121), and OMCA should have D2300118 (and PZT cable D2300120), and I installed them opposite according to the DCPD cables. This doesn't account for the wiring issue; it would only make a cable length difference.
Oli and I went into the lab to swap around OMCA and OMCB, and realized that one OMC has the DCPD cable for A (D2300118) and PZT cable for B (D2300121) and vice versa. So it's not clear which is which.
Keita has further pointed out that this wiring issue with the grounding pins could indicate cathode and anode are swapped, which means that the diode will be forward biased, which is a much bigger issue.
Therefore, we're pausing on all BHSS work for now until we can figure out how to resolve these problems.
LLO has not checked their wiring, but Oli and I did note that they paid attention to the OMC labeling since they knew the cable lengths would be different.
When our OMCs were shipped to us, the ameristat wrapping had OMC A and OMC B labels, but once we took the wrapping off, there was no indication of A and B on the boxes.
Keita, Elenna, and I just went in and tested the direction the current is flowing for the DCPD cables (D2300118 and D2300119).
D2300118 (SN S2500546)
Current direction:
- Pin 2 -> 1
- Pin 5 -> 4
D2300119 (SN S2500548)
Current direction:
- Pin 6 -> 1
- Pin 9 -> 4
We verified that there was no current flow when probes were swapped
For posterity, Ali etc. confirmed that the bias voltage is carried by pin 1 and 4 between the DCPD and the in-vac frontend: https://alog.ligo-la.caltech.edu/aLOG/index.php?callRep=80660
This means that the latest (fixed) version drawing for DCPD-D9M (https://dcc.ligo.org/D2300118-v2 and https://dcc.ligo.org/D2300119-v2) are correct, which is a good news!
This also means that the wiring diagram https://dcc.ligo.org/D2000592 is incorrect and the circuit diagram for the in-vac frontend https://dcc.ligo.org/D2200276 is incorrect or lacking information about the connection between the D9M feedthrough and the D9M connector on the board (e.g. the connection cable inside the box is not a usual cable but gender-changer type).
Elenna, Oli
Summary: OMCB has its DCPDs installed and most of its stoppers (barring one that needs to be retapped + helicoiled). OMCA has been aligned according to the OMCA / OMCB install template and is ready for laser alignment. Cabling for both OMCs should be good to go.
After last week's issue of the OMCB DCPD A (TRANS) missing a diode hole (89583), we were able to clear up the issue and fix it (89606). Elenna then installed the DCPD B (REFL) diode. Note that once again there were tiny metal shavings below where the DCPD's were installed, which we picked up with a qtip that we wet with iso. Once we had both installed (pic), we installed the rest of the stoppers around OMCB. The only one we didn't install is one of the vertical stops. This is because there was an issue with the helicoil last week, and we ended up having to remove it. We think this might be due to an issue with the threads, so we are waiting on a 3/8"-24 tap to retap the hole before installing a new helicoil. Because we don't have this stop yet, it doesn't really make sense to fasten on the butter dish, but we might just sit it on today to hinder dust accumulation.
We also realized that the PZT cables were going to be way too short to reach the cable pylons for both OMCA and OMCB, so we very carefully opened the peak cable wraps on the OMCs and took out what we think should be enough. On OMCB we noticed that the little copper wrap for one of the PZTs was not right above the PZT as it should be, but instead was on the other side of the peak cable wrap and was only wrapped loosly around one of the cables. Because of this we just removed the wrap. The cables right above the PZT are looking fine and don't look like they need anything to hold them together.
I had been confused about the OMCA / OMCB install template for the past few days, since installing it was putting OMCB further back in its slot than OMCA, but I was able to confirm yesterday in eDrawings that OMCB is actually supposed to be an extra 1 mm away from the front of its slot as compared to OMCA, so we moved OMCA into position and bolted it down.
I also went in and installed the magnet mounts for the OSEM magnets (without the magnets), as well as the big mass on the back of the BHSS.
Installed serial numbers:
OMCB (SN 105)
Tagging For EPO photos.
The naming convention listed above is incorrect. Please refer to alog 89669 for correct information.
Elenna, Keita, Oli
Input alignment:
Today Elenna and I finished fine-tuning the alignment into the BHSS, so now our beams pass through both sets of irises on the alignment tooling plate, so they should be well aligned to go into the OMCs nicely.
OMCA in cradle:
We also opened up what is going to be OMCA (SN 103) and placed it in its cradle. We followed the installation instructions and placed the OMC 1mm away from the three installed horizontal stops, but then we noticed that lining the short end up against the side horizontal stop led to the OMC overhanging the cradle on that side by a few mm. We're not sure if these end stops are also supposed to be further inwards than 1mm (the instructions just specify that they (the horizontal stops) will be touching the OMC 1mm in), but if we placed the other end stop in with the way that the OMC is currently positioned, that other stop would have to screw in at least 3 or 4 mm to meet up with the OMC. We will add photos of this tomorrow.
Installing DCPDs onto OMCA:
Keita and Elenna (who was chained to the optics table via grounding strap) very carefully trimmed the DCPD wires for D1-20 and C1-12 and placed them in the DCPD mounts for DCPD A (which is what we think TRANS is), and DCPD B (which is what we think REFL is), respectively. Faceplate SN 10 was installed onto DCPD A, and faceplate SN 06 was installed onto DCPD B to hold the PDs in place. It was very hard to get the length of the DCPD pins right, and getting the faceplates on and secured. There seems to be a small gap in between the faceplates and the DCPD housing (pic1, pic2), but LLO has the same thing happening so it seems okay.
Checking pins
After we used a multimeter to check that the case pins followed D220027. According to D220027 the case pins should be going to pins 6 and 9, but we found that they went to what we thought were pins 1 and 4 when we were looking at the prongs. Later we found that the DB9 pin layout is read the other way, so that means that it was actually pins 2 and 5. This still doesn't line up with D220027, but looking at the schematic for the cable D2300119, it turns out that the wires for the Cases for the two DCPDs are shifted so that the Cases do actually go to pin 2 and pin 5, so they're wired correctly! It's just that D220027 is wired up incorrectly and appearantly the cable pins are read with the prongs facing away from you for some reason.
OMCA is looking pretty good so far! (pic3, pic4)
Summary of installed serial numbers:
OMCA (SN 103)
Here are photos of the OMC overhang when the OMC is 1mm away from the horizontal stop (set screw is in by 1mm), and photos showing the other end.
other angle
The naming designation listed above for DCPDA/B is incorrect. Please refer to alog 89669 for correct information.