corey.gray@LIGO.ORG - posted 15:36, Tuesday 10 October 2017 - last comment - 15:56, Tuesday 10 October 2017(38975)
IO Items Removed From HAM2 Today + Checking/Tightening IM3 Assembly Screws

(Cheryl, Corey, Ed, Keita)

Items Removed 

The following assemblies/items were removed today & bagged/tagged:

ROM RH4:  

ROM RH5:

NOTE:  The 2" HR ("M-38-UNP-53") & Black Glass dump for this one was installed on ROM RH4

ROM RH6:

ROM LH2:

NOTE:  A V-Black Glass Dump was installed on the post for LH2.

Misc:

Tightening IM3 Assembly Screws

Here is a note Ed wanted me to take while Keita tightens:

1)  Tightened screws on top of IM3, and had this:

2) Tightened 1/4-20 bolts (on sides, OSEM plates, etc.), and had this:

 

Comments related to this report
edmond.merilh@LIGO.ORG - 15:56, Tuesday 10 October 2017 (38977)
  • IMG-2655 shows overhead view of the black glass beam dump that was added (9:00 position in photo)
  • IMG-2656 shows the HR optic w/black glass which replaced the 90/10 BS that was there before
  • IMG-2658 shows the vacant space where there were two HR mirrors (one of which resides where the BS used to)
  • IMG-2659 is a close up of the mirror that replaced the BS
Images attached to this comment