Reports until 15:53, Thursday 13 February 2014
H1 General
jeffrey.bartlett@LIGO.ORG - posted 15:53, Thursday 13 February 2014 (10074)
Ops Summary
LVEA Laser Safe

Hanford FD on site testing fire alarms at End-X and End-Y

08:59 Corey - in LVEA looking for cables and then going to End-y
09:00 Hugh, Mitch, & Justin – Adding payload to HAM4 ISI
09:17 Betsy – Going to End-Y
09:32 Filiberto & Aaron – At End-X working on ISI cabling
10:00 Hanford FD – Completed testing and left site
11:13 Hugh, Mitch, & Justin – Completed adding payload to HAM4, out of LVEA
12:00 Corey & Betsy – Back from End-Y
12:46 Karen – Cleaning at End-Y
12:50 Dave – Making updates to PDM model
12:50 Filiberto & Aaron – Back to cabling pulling at End-X
12:53 Dave – DAC restart
12:57 Justin – Transitioned LVEA to Laser Hazard
13:10 Mitch & Jim – Working on HAM4 ISI
13:30 Hugh – Going to End-Y
14:32 Filiberto & Aaron – Going from End-X to End-Y
15:30 Mitch & Jim – Finished at HAM4, out of LVEA