Here is the list of commissioning task for the next 7-14 days:
Green team:
-
Hand-off to red
-
Noise measurement between red and green locked on red.
-
Make a mode scan of the red resonances.
-
ETM drive diagonalization for length and angle.
-
ITM drive diagonalization for angle.
-
Commission the length feedback path to the ETM top suspension point to suppress microseism.
-
Camera for ITMX face view (possible?)
Red team:
-
Center the red QPDs in EX.
-
Investigate the robustness of the 3f lock in presence of an arm cavity.
-
Start commissioning the alignment system. REFL_A commissioning.
-
Optimize the thermal compensation of ITMY.
-
Investigate the REFLAIR45 whitening filter issue.
Blue team (ALS WFS):
-
Test electrical connections.
-
Use AM laser to test RF signal chain.
-
Beam quality investigation.
-
Measure sensing matrix.
Blue team (ISCTEY, delayed):
-
Prepare second set of WFS Complete the feedthrough panels.
-
Install the on table cabling.
-
Prepare for move to the end station.
-
Check out ALS electronics in EY.
-
Add WFS.
TMS:
-
Ground loop investigation.
-
Beam alignment in final position.
SEI/SUS team:
-
Improve stability under high performance for ETMX.