Displaying report 1-1 of 1.
Reports until 13:55, Tuesday 18 February 2014
H1 SEI (INS)
jim.warner@LIGO.ORG - posted 13:55, Tuesday 18 February 2014 (10149)
ETMY ISI floating, leveled, testing started

This morning, with a little help from Hugh, I finished preparing the ISI for chamberside check out. I replaced the bad St1H3 cps, fixed some cable routing issues, then floated and balanced the stages. All went relatively painless, aside from the chaotic, cramped quarters in the end station (cables EVERYWHERE!). Now, all the sensors seem functional and I've started running some basic tests. Should be starting on tf's soon.