Green team:
-
Stabilize the red/green difference using a slow feedback path.
-
Hand-off to red.
-
Noise measurement between red and green locked on red.
-
Make a mode scan of the red resonances.
-
ETM drive diagonalization for length and angle..
-
ITM drive diagonalization for angle.
-
Centroid fit for ITMX camera..
Red team:
-
Commissioning of the initial dither alignment system.
-
Fix: BS feedback triggering an ISI trip.
-
Center the red QPDs in EX.
-
Investigate the robustness of the 3f lock in presence of an arm cavity
-
Start commissioning the alignment system.
-
REFL_A calibration.
-
Optimize the thermal compensation of ITMY.
-
Investigate the REFLAIR45 whitening filter issue.
-
PRC length measurement.
Blue team (ALS WFS):
-
Stability investigation.
-
Re-measure sensing matrix.
-
Beam quality investigation.
-
Diagonalization of dither alignment feedback.
Blue team (ISCTEY, delayed):
-
Prepare second set of WFS Complete the feedthrough panels.
-
Install the on table cabling.
-
Prepare for move to the end station.
-
Check out ALS electronics in EY.
-
Add WFS.
TMS:
-
Ground loop investigation.
-
Beam alignment in final position.
SEI/SUS team:
-
Install optical lever damping for vertical and roll modes.
-
Improve stability under high performance for ETMX.
-
Fix: TwinCAT reboot trps HAM ISI.