H1 SEI (INS, ISC, SEI, SUS)
hugh.radkins@LIGO.ORG - posted 16:21, Monday 24 February 2014 - last comment - 10:05, Tuesday 25 February 2014(10287)
ETMY Cartridge Landed in Chamber--Last for H1!

No issue to report other than missing zippers on the SEI Ceiling Sock.

Clean room back up with the Cartridge ready to go down at lunch.  Torqued to Support Tubes and closed up by 1430pst.

Thanks to Apollo Scott, Mark & Bubba, SUS Travis and SEI Jim.

Corey helped too and took lots of photos.

Images attached to this report
Comments related to this report
michael.landry@LIGO.ORG - 10:05, Tuesday 25 February 2014 (10306)INS
Congratulations all for reaching this milestone safely.  That's five H1 cartridge insertions, plus the two for H2 chambers BSC6 and BSC8.  Nicely done!

Remaining in-chamber installation includes:
  • close out BSC10 at EY and pump down for dual arm experiment
  • populate existing HAM5 ISI with SUS, AOS components
  • temporarily pull septum at HAM6 and align SRs in HAMs 4 and 5 from the end door of HAM6
  • vent the vertex, swap ITMs for production masses in BSC1 and BSC3
  • pull associated manifold spools and align ITMs; install y-arm CPB and ACB
  • pull the temporary septum at HAM4 and align HWS in HAM4