Reports until 17:06, Tuesday 25 February 2014
H1 SEI (INS, ISC, SEI)
hugh.radkins@LIGO.ORG - posted 17:06, Tuesday 25 February 2014 - last comment - 17:17, Tuesday 25 February 2014(10329)
EndY Field Cabling Work Update

Not sure if Filiberto is complete but maybe...

As far as SEI work goes:

CPS racks are located and all wired up sans sync cable.

~75% of the in-air cables going to the Feed Thrus are Strain Relieved.

The harder half of the Dial Indicators are in place.

Comments related to this report
filiberto.clara@LIGO.ORG - 17:17, Tuesday 25 February 2014 (10330)
Cabling for SUS, ISC, and SEI are pulled and and connected to the feedthrus except for ISI Corner 1 Flange F6. Flange has DB25 connectors but should be 3 pin power connectors.

Filiberto Clara