H1 SEI (INS, ISC, SEI)
hugh.radkins@LIGO.ORG - posted 15:57, Wednesday 26 February 2014 - last comment - 16:49, Wednesday 26 February 2014(10360)
WBSC10 In-Field cables attached & secured--other activities

Replaced the incorrect feed thrus with the needed 3-Pin power style.  Then completed the cable attachment, cable strain relief and finally the easier half of the Dial Indicators.  Almost that is--I was short three 5" bolts to strain relieve some SUS cables on the South side.  I must have cut myself a little to close wrt inventory.  But generally, all the really needed dirty work is done.

The Apollo crew got Test Stand, extra Spiral stair case, 3P spreader, and a few other things from the VEA.

The cleaning crew jumped right on as soon as I was out of the way--a few dust alarms with that work.

Comments related to this report
hugh.radkins@LIGO.ORG - 16:49, Wednesday 26 February 2014 (10361)

Crud--I forgot the CPS sync cables...Will be routed on the South & West side--away from the open door.