Chamber cleaning work continues throughout the day in BSC 7. 9:15 - Gregorio at mid-y 11:00 kyle and Gerardo to soft close a gate valve mid columbia forklift 11:45 1:45 – Mike L. and Gerardo to check out beam baffle in LVEA Kyle informed the control room that the channel PT 134 B will alarm once the value drops below 1e8 torr. This level is expected and the alarm can be ignored for now. The alarm level will need to be changed to prevent the trigger.