Reports until 17:33, Wednesday 13 July 2011
LHO FMCS
kyle.ryan@LIGO.ORG - posted 17:33, Wednesday 13 July 2011 (1050)
Moved diagonal volume purge connection
In order to facilitate the removal of BSC4's dome I relocated the purge air connection from BSC4's dome to HAM9.  I had to remove the 10" CFF blank located on the lower right of the West door of HAM9 and install a Class A 10"-2.75" zero length reducer in its place.  This reducer is labled as "interim" and is held on by only (3) bolts.