greg.grabeel@LIGO.ORG - posted 09:00, Thursday 14 July 2011 (1052)
HAM 10 HEPI Install

HAM 10 now has the HEPI piers, enclosures, and crossbeams installed. The support tubes have not been leveled yet but will be today.

The west side lifted up when the crossbeam was placed first on the east side. I think this could be reduced by clamping the crossbeam down while it is still supported by the crane. This, however, would monopolize even more time with the crane. It has been possible to adjust the height with the set screws on the HEPI foot, but this has been fairly difficult and the screws bind occasionally. So the less height adjustment needing to be done from the foot the better.

Images attached to this report