Displaying report 1-1 of 1.
Reports until 16:02, Friday 15 July 2011
LHO FMCS
dani.atkinson@LIGO.ORG - posted 16:02, Friday 15 July 2011 (1056)
Ops Day Shift Summary
  • BSC4's dome was floated and placed back in position successfully.
  • Chamber cleaning continues to continue in BSC7.
  • HEPI installation is presumably still happening somewhere.
  • More work setting up ISI test stand #2.
  • Prep work at MX for the removal of BSC5.