Ops Day Shift Summary
BSC4's dome was floated and placed back in position successfully.
Chamber cleaning continues to continue in BSC7.
HEPI installation is presumably still happening somewhere.
More work setting up ISI test stand #2.
Prep work at MX for the removal of BSC5.