.......LVEA: Laser SAFE..............EY: Laser SAFE.........EX: Laser HAZARD.......
A major activity today was the installation of the Spool at EY, installation of viewports on the spool, and then getting PCal pylons staged into position. Other activities are:
-
Jeff: Dust Monitor #1 in LVEA is in HAM5 cleanroom--had INVALID alarms most of the day, so it is currently offline to charge overnight.
-
JAX checking for shorted cable at ISCTEY
-
Justin heading to EY & EX to check stuff (900-945)
-
Betsy: working at ITM build area most of the day
-
Mitch West Bay Clean-up (925-955)
-
EY #1 dust monitor is at the spool clean room for spool installation, it had a blown fuse and it was replaced, and should now be online
-
Filiberto: HAM4 cable pulling
-
Jax: heading backto ey
-
Cyrus: working on PEM rack at MY
-
gerardo: ofi work in H2 psl room
-
Jeff/Andres: Working on SR3. Running TFs now
-
SEI Measurements at EY 2-4pm? But HEPI tripped during measurement
-
Travis: searching for weld panels at end stations
-
Justin & I (with help from Arnaud) followed Sebastian's instruction for bringing back a few BSC ISIs from Watchdog Trips