Reports until 08:39, Wednesday 20 July 2011
X1 SEI
corey.gray@LIGO.ORG - posted 08:39, Wednesday 20 July 2011 (1075)
BSC ISI #2 & #3 Assembly Status

(Corey, Jim)

BSCISI#2

Cleared out the cleanroom of clean parts and covered the ISI system, so hole-drilling could occur on the Test Stand (these holes are for the Cabling Interface Panels).  2/3's of the holes were drilled yesterday.

BSCISI#3

Finished off helicoiling parts for the Small Actuators.  Large plates probably won't be loaded in the oven until Thursday (making them available some time early next week).