Reports until 16:07, Wednesday 19 March 2014
LHO General
gerardo.moreno@LIGO.ORG - posted 16:07, Wednesday 19 March 2014 (10872)
Ops Summary

8:49 am, Aaron to Y-End, stage relay for noise eater.
9:04 am, Apollo to LVEA, move in scissor lift into LVEA via the high bay area, to remove pre-filters from HAM5 cleanroom.
9:15 am, Corey, Jax and Keita to Y-End, TMS work.==>out by 11:40 am.
9:52 am, Aaron to LVEA, move rack by HAM4/BSC3 area for TCS.
10:19 am, Jeff and Adres to LVEA, do chamber side work inside cleanroom by HAM4/5.
10:29 am, Filiberto to LVEA, to visit both spool pieces to terminate OL cables.==>done by 11:30 am.
10:35 am, John to X-end, inspection of VEA area.==>done by 10:35 am.
11:01 am, Karen to Y-End, clean.==> done by 11:31 am.
11:02 am, Betsy to LVEA, west bay area, ITM assembly.
11:25 am, Craig C to LVEA, work inside H2 laser enclosure.
12:55 pm, Corey to Y-End, TMS work.
1:00 pm, Sheila to X-End, ==>done by 1:21 pm.
2:16 pm, Apollo, Jeff and Kate to LVEA, door removal from HAM5.==>Jeff and kate out by 3:29 pm, Apollo out by 3:36 pm.
2:40 pm, Kyle to Y-Mid, hard close GV10.
3:34 pm, Cyrus and Jim to LVEA, West bay area work.==>done by 3:45 pm.

Displaying report 1-1 of 1.