Reports until 15:25, Thursday 20 March 2014
H2 SEI (SEI)
mitchell.robinson@LIGO.ORG - posted 15:25, Thursday 20 March 2014 (10903)
Staging building, 3IFO (unit 2) progress
Jim, Mitchell
The down facing optical table is now parked on the granite table anxiously awaiting Apollo on Monday. The up facing is on the assembly stand also ready for action.

As for unit 2 the small and large horizontal actuators have been installed. Stage 1 doors prepped. Horizontal L4-C's have also been installed. Some of the blade bending fixtures have been added.