H2 General
corey.gray@LIGO.ORG - posted 13:16, Tuesday 26 July 2011 (1100)
BSCISI#1 Work

(Corey, Hugh, Vincent)

Checked Level of the Optics Table and also took shots of the top of Stage0 (where the Alignment Pin cut-outs are).  Optical Level was used for level-checking.

While working around the table, removed the Alignment Pin Washers for Stages1-2 & Stages0-1 (thought it would be a good idea to not leave these loose items on floated stages).  There is a photo (which needs to be rotated clockwise 90deg) of where these washers are located.  The Stage1-2 Washer is a little tough to retrieve, but it was pulled out with the use of a small allen wrench.

Took opportunity to pull lots of lingering hardware and tools which were "stored" on Stage0. 

Vincent wanted to check the big masses (Leg Elements) on top of the Keel (Stage2) for any possible vibrations.  Sure enough, the smaller (~200lb) masses on top of the bigger masses did have some observable gaps underneath them.  [tried to snap some camera-phone photos to illustrate this].

Images attached to this report