michael.rodruck@LIGO.ORG - posted 16:12, Tuesday 26 July 2011 (1103)
H2 PSL Installation

More framing work for the diode and chiller rooms. The ceiling joists have been added. No construction work tomorrow, but on Thursday they will start cutting into the LVEA drywall. The North crane is still tied up.

Dust counts are again low. A trend of the last 10 hours is included.