Here is the list of commissioning task for the next 7-14 days:
Green team:
-
Look for the source of the 1/f noise.
-
Look for clipping in green transmission.
-
Make a mode scan of the red higher order modes.
-
Test the length feedback path to the ETM top suspension point to suppress microseism.
Red team:
-
Center the red QPDs in EX.
Blue team (ALS WFS):
-
Reduce beam size on sensor head.
-
High bandwidth WFS.
Blue team (ISCTEY):
-
PLL fiber locking.
-
Add WFS.
SEI/SUS team:
-
Commissioning optical lever.
-
PUM range for ETMs.
-
ETMY diagonalization.