mitchell.robinson@LIGO.ORG - posted 16:33, Wednesday 09 April 2014 (11255)
Staging building, 3IFO (unit 3) progress
Yesterday,
Scotty and I were able to populate the 400+ 1/4-20 hardware into the stage 2 closeout plate cover, as well as attach the back and side ribs. 

Today,
I made a cable kit for 3IFO BSC unit 2. Unit 3 will need 4 cables tested before it is a complete kit. All bolts connecting the closeout plate and closeout plate cover were torqued to spec. Locker sub-assemblies have begun. General cleanup and shelf organization is also ongoing.