gerardo.moreno@LIGO.ORG - posted 17:26, Thursday 10 April 2014 (11276)
ALS Shutter Replacement

(Joseph D., John W., Justin B., Sheila D.,  and Gerardo M.)

Attempted to install new ALS shutter, but as soon as we started we found 3 scratches on the viewport (inside side), see photo, John was consulted and the decision was to abort the rest of process, first contact was not applied to viewport, and the rest of the components were staged to finish work tomorrow.  GV7 will remain soft closed until then.

Images attached to this report