Reports until 17:32, Tuesday 15 April 2014
H1 TCS
david.hosken@LIGO.ORG - posted 17:32, Tuesday 15 April 2014 - last comment - 09:35, Wednesday 16 April 2014(11372)
TCS update/status
DavidH, Greg, Thomas

TCSX: Plumbing sorted (except for one last connection to water-cooled beam dump, awaiting fittings), optics mounted and optical mounts are positioned on the table ready for alignment. Optics that are not within table are accounted for. Last few cables are to be connected.

TCSY: Enclosure re-cleaned, plumbing connected up (except for beam dump) and water manifolds in final positions, laser/RF driver cables are all dressed and connected to feed-throughs.

See images for current TCSX/Y table layouts
Images attached to this report
Comments related to this report
justin.bergman@LIGO.ORG - 06:45, Wednesday 16 April 2014 (11374)

Have we located the keys for the table door locks?

greg.grabeel@LIGO.ORG - 09:35, Wednesday 16 April 2014 (11380)
They were found in the enclosure after David was able to tidy up.