Co-ordination Planning for LVEA this week
Co-ordination Planning for LVEA
02-05 August 2011

Tuesday, 02 Aug 2011-Laser Hazard
	Kyle to remove pump cart from near BSC-8 and hard-close GV-5
	Richard / Apollo to slide the ISI racks forward to accommodate survey crew on Y-arm
	ICC to stage all possible items to the PSL-1 area, including 2 garbing/staging cleanrooms
Wednesday, 03 Aug 2011-Laser Safe-Crane work restricted during shots
	Doug and crew to take required shots along Y-arm
	Kyle to vent volume needed for BSC-8 entry?
Thursday, 04 Aug 2011-Laser Safe-Crane work restricted during shots
	ICC to move large cleanroom over BSC-8 chamber (as long as shots are finished) 
	ICC to remove cleanroom from BSC-7 and set it down out of the sight lines for new H2 shots (Dome cleanroom)
	Doug and crew to take required shots along X-arm
Friday, 05 Aug 2011-Laser Safe-Crane work restricted during shots
        ICC to move dome cleanroom into place near HAM 11-12 (as long as shots are finished)
	Doug and crew to complete survey work