Co-ordination Planning for LVEA
02-05 August 2011
Tuesday, 02 Aug 2011-Laser Hazard
Kyle to remove pump cart from near BSC-8 and hard-close GV-5
Richard / Apollo to slide the ISI racks forward to accommodate survey crew on Y-arm
ICC to stage all possible items to the PSL-1 area, including 2 garbing/staging cleanrooms
Wednesday, 03 Aug 2011-Laser Safe-Crane work restricted during shots
Doug and crew to take required shots along Y-arm
Kyle to vent volume needed for BSC-8 entry?
Thursday, 04 Aug 2011-Laser Safe-Crane work restricted during shots
ICC to move large cleanroom over BSC-8 chamber (as long as shots are finished)
ICC to remove cleanroom from BSC-7 and set it down out of the sight lines for new H2 shots (Dome cleanroom)
Doug and crew to take required shots along X-arm
Friday, 05 Aug 2011-Laser Safe-Crane work restricted during shots
ICC to move dome cleanroom into place near HAM 11-12 (as long as shots are finished)
Doug and crew to complete survey work