Ops Morning Summary
08:50 Corey, Thomas staging viewport covers by LVEA X arm beam manifold
Kyle soft closed GV7
08:58 Betsy, Travis getting parts from ITM build area
09:11 David H, Matt H. working on TCSX, TCSY
Kyle to open GV5, GV18
09:27 Alexa to end Y to take fiber noise measurements
09:27 Richard done installing lexan viewport cover