Displaying report 1-1 of 1.
Reports until 09:09, Wednesday 23 April 2014
H1 SUS (CDS, ISC, SYS)
jeffrey.kissel@LIGO.ORG - posted 09:09, Wednesday 23 April 2014 (11526)
Beginning Installation of ASC to SUS Dither Paths, ECR E1400105
J. Kissel (Approved by M. Landry, K. Kawabe, V. Sandberg)

I'm taking the opportunity while gate-valves are closed for TCS table moving to install ASC dither alignment IPC channels into all core-optic SUS, (see ECR ). This will replicate what has been done for PR2 (see LHO aLOG 10346). Note, for now (so the SUS models will compile without complaint), I plan to add the IPC sender channels at the top-level of the ASC model, with zeros sent into them, and I'll leave it up to the ISC team to hook them up to their main library block as they wish.

The models affected with be 
(to add new IPC sender parts)
h1asc

(to add new IPC receiver parts)
h1susprm
h1suspr3
h1susbs
h1susimty
h1susitmx
h1susetmx
h1susetmy
h1sussrm
h1sussr2
h1sussr3

[because it uses the HSTS_MASTER, MC_MASTER library part, so new unused inputs must be terminated]
h1susmc1
h1susmc2
h1susmc3

(to add dither paths to each stage of each SUS type)
SIXOSEM_F_STAGE_MASTER
FOUROSEM_STAGE_MASTER
FOUROSEM_STAGE_MASTER_OPLEV
SIXOSEM_T_STAGE_MASTER
QUAD_MASTER
BSFM_MASTER
HLTS_MASTER
HSTS_MASTER
MC_MASTER

Work beginning 
1082304916
2014-04-23 16:15 UTC
2014-04-23 09:15a PDT

I'll make sure to capture a new h1asc_safe.snap before getting started. 
Displaying report 1-1 of 1.