815-828
mike, daniel, stefan, aiden, terry, bubba, margot, ski, matt h, jason, patrick, hugh, jeff, jodi, andres, corey, richard, pablo, david H, jimW, thomas, filiberto
-
LVEA Laser HAZARD, but will be made SAFE until afternoon, and then back to HAZARD
-
HAM5--cleaning being done, cleanroom modified yesterday (JeffB will inspect)
-
Septum: bolts being pulled, plan to remove today & cover septum hole
-
Will be reinstalled later, and then have windows installed (may require holes being tapped in septum?)
-
TCS: yesterday both TCS tables pushed up against BSC & alignment work
-
HAM5 ISI: SEI crew will need to strip ISI of stuff with forklift when OK to work in-chamber
-
bscs press sensor work at end stations--EX first (richard & crew)
-
commissioning work: alignment work in morning & then beatnote work & electronics troubleshooting if necessary
-
staging: 3ifo BSC ISI work continues