Here is the list of commissioning task for the next 7-14 days:
Blue team (Y-arm):
-
Fix demodulator.
-
Arm length measurement.
-
Finish WFS cabling.
Blue team (X-arm):
-
Revisit the WFS with the now improved beam quality.
Green team (XY-arm):
-
Install ESD drive in Y End.
-
ALS DIFF locking
-
Noise hunting.
-
Restablish PRMI.
-
Measure relative motion between green/red beams.
Red team:
-
Center the red QPDs in EX.
SEI/SUS team:
-
SUS/SEI tuning
-
Setup alignment dither.
-
Commission EY ESD drive.
-
Commission high bandwidth length drive to SUS/ESD.