Very short (under 5min meeting!)
-
HAM5 alignment work continues: Setting up for pit/yaw check of SR2 (Jason & crew)
-
TCS: hartman sensor table work most of the day; TCSy Table/Laser work in afternoon by Alastair
-
SEI in LVEA on hold until SR2 work done (Hugh)
-
EY ESD work continues in morning (Richard)
-
Locking ongoing; saturation investigations (Stefan reporting)