Here is the list of commissioning task for the next 7-14 days:
Green team (XY-arm):
-
ALS DIFF locking.
-
Hand-off ALS signals to interferometer signals.
-
Noise hunting.
-
Make a measurement of input HAM/IMC motion using POP and the red reference beam.
Blue team (Y-arm):
Blue team (X-arm):
-
Revisit the WFS with the now improved beam quality.
Red team:
-
Reestablish PRMI.
-
Center the red QPDs in EX/EY.
SEI/SUS team:
-
Setup alignment dither.
-
Commission EY ESD drive.
-
Commission high bandwidth length drive to SUS/ESD.