Reports until 16:43, Monday 08 August 2011
H2 General
jonathan.berliner@LIGO.ORG - posted 16:43, Monday 08 August 2011 (1174)
Monday Ops Log
- DougC and JasonO taking shots in LVEA...done by ~1425
- ICC staging at BSC8, Kyle cranes pump cart over YBM and plans on commencing pump down soon
- Welcome MichaelS from ANU
- Reibold finishes dry wall by H2 PSL Diode Room, finishing touches remain
- Pipe welding at EX
- Alignment of BSC5 continues at EX
- RichardM investigates H2 overhead camera's signal which is flickering terribly on all displays.  Problem seems to be upstream from MSR
- BetsyB, JeffB, AndresR, EricA working in West Bay test-stand area
0918 - Hanford Fire Department arrives to check outbuildings
1300 - Diamond Freight arriving for pick-up
1400 - MikeL visits outbuildings
1440 - Laser Hazard in LVEA
1600 - DanM running cable from Computer Users' Room (LDAS tape library) to MSR under raised floor in Control Room