H1 ITMy ACB build

Mitchell, Margot, Myself

 

Over the past two days, we have managed to re-launch ACB assembly in the LVEA teststand cleanrooms.  The first day was largely clearing space in the cleanrooms and locating and reclaiming parts (most of the parts had prematurely been put into 3IFO storage).  By the end of today, we have the baffle box mostly assembled, with the exception of the extension due to running out of, of all things, 1/4-20 washers.  More washers have been located in SUS stock.  Tomorrow, we plan to wrap up assembling the baffle and move onto the suspension.