patrick.thomas@LIGO.ORG - posted 08:45, Thursday 08 May 2014 (11764)
Installation meeting notes
SR2 is aligned.

SR3 was installed last night. It will be clamped down and wired today.

Betsy is working on baffle installation in HAM4. There are issues with the cookie cutters.

No TCS projection likely today. This is Matt's last day. He would like laser hazard ASAP.

WFS work is on hold.

Staging the ITM in the beer garden is on hold.

A faulty ESD cable at end X was found and fixed yesterday. Work continues today.

Work on 3rd IFO assembly continues in the staging building.

Joe D. wants to get access to a box at mid Y. This will require craning another box out of the way.