Earthquake tripped ISIs last night, looks like it's the one off the coast of Oregon 5.1 @ 10km.
Install Activities:
- TCS Team is going to work on HWS table until 2 PM and then go to laser hazard and align the CO2Y table, CO2X's overnight run looks like its working well.
- HAM5 SR3 alignment is ongoing with Jason and Jeff. After they're done with the alignment, fine adjustments and transfer functions will begin.
- Margot and Travis are working on ACB assembly, Mitch gave a hand yesterday but he might be working with SEI today
- Staging building work is ongoing with SEI team with help from Scotty from Apollo. Fabrice wants to take magnetic coupling measurements.
- ESD work is ongoing, both end stations have their various problems. The problem could be in-vacuum and might need the June vent to fix although the problem has not been precisely determined yet.
- Integration is ongoing, some progess last night but a few problems.
- During June-July vent, it's probable that we'll be implementing wire-hung baffles on BS and an ISS on HAM2
Maintinence:
- LN2 @ EX
- Jeff Kissel is going to implement new SUS code
- Christina and Terry are going to take stuff off-site