Reports until 16:13, Wednesday 14 May 2014
LHO General
Link
corey.gray@LIGO.ORG -
posted 16:13, Wednesday 14 May 2014
(11881)
Ops DAY Summary
Day's Activities
6:30am ETMy measurement ran (was done early morning)
MY low pressure sensor still valved off causing alarm
SRM Install work begins (Jeff, Andres, Betsy)
9:10am Pulling cable at end stations (Aaron)
9:15am David/Greg working on Hartman table
Kyle will be doing Vacuum system work today
9:20-11:44am SRM Alignment set-up (Jason)
10:05am Travis/Mitch ACB work
~10am Dust Monitor #5 went to a few thousand counts (but didn't receive an alarm for it)
11:20am Richard/Fil heading to EY for ESD work
KEPR film crew on-site. (will broadcast at 5 & 6pm)
afternoon--EX ESD work (Richard/Kissel)---swapping out chasis
High dust counts in the Beer Garden (Jeff investigated)
ISS PD Array in the H2 Laser Enclosure Room (they will be going to Laser Hazard in their room)
Since EX & EY are closed up, I increased the Dust Monitor Alarm levels to 500counts (MIN) & 1000counts (MAJ)
Transitioning to Laser HAZARD after Safety Meeting