Reports until 16:13, Wednesday 14 May 2014
corey.gray@LIGO.ORG -
posted 16:13, Wednesday 14 May 2014 (11881)
Day's Activities
-
6:30am ETMy measurement ran (was done early morning)
-
MY low pressure sensor still valved off causing alarm
-
SRM Install work begins (Jeff, Andres, Betsy)
-
9:10am Pulling cable at end stations (Aaron)
-
9:15am David/Greg working on Hartman table
-
Kyle will be doing Vacuum system work today
-
9:20-11:44am SRM Alignment set-up (Jason)
-
10:05am Travis/Mitch ACB work
-
~10am Dust Monitor #5 went to a few thousand counts (but didn't receive an alarm for it)
-
11:20am Richard/Fil heading to EY for ESD work
-
KEPR film crew on-site. (will broadcast at 5 & 6pm)
-
afternoon--EX ESD work (Richard/Kissel)---swapping out chasis
-
High dust counts in the Beer Garden (Jeff investigated)
-
ISS PD Array in the H2 Laser Enclosure Room (they will be going to Laser Hazard in their room)
-
Since EX & EY are closed up, I increased the Dust Monitor Alarm levels to 500counts (MIN) & 1000counts (MAJ)
-
Transitioning to Laser HAZARD after Safety Meeting