Installation Meeting Minutes
Wed: went over Work Permits
Commissioners on site till ~7am
SR3 finished, TF initials look good (HAM5)
SRM alignment prep, SRM optic working on getting it in first part of day, may push laser hazard past 2pm (HAM5)
Arm Cavity Baffle work continues all day
Cryo Pump Baffle assy slated for June
TCSx laser good, TCSy had some optics in wrong spot (realign whole table?), Hartman work cont.
Elec: EY ESD cont, cable pulling at EY/EX
HAM4 cookie cutters still being fabricated holding up HAM4 work
Staging bldg work ongoing (assy & testing)
Guardian work: ITMy testing, hepi guardian running, testing manager code, can work till noon today
There WILL BE a safety meeting at 3pm