Reports until 08:38, Wednesday 14 May 2014
corey.gray@LIGO.ORG -
posted 08:38, Wednesday 14 May 2014 (11882)
Installation Meeting Minutes
-
Wed: went over Work Permits
-
Commissioners on site till ~7am
-
SR3 finished, TF initials look good (HAM5)
-
SRM alignment prep, SRM optic working on getting it in first part of day, may push laser hazard past 2pm (HAM5)
-
Arm Cavity Baffle work continues all day
-
Cryo Pump Baffle assy slated for June
-
TCSx laser good, TCSy had some optics in wrong spot (realign whole table?), Hartman work cont.
-
Elec: EY ESD cont, cable pulling at EY/EX
-
HAM4 cookie cutters still being fabricated holding up HAM4 work
-
Staging bldg work ongoing (assy & testing)
-
Guardian work: ITMy testing, hepi guardian running, testing manager code, can work till noon today
-
There WILL BE a safety meeting at 3pm