andres.ramirez@LIGO.ORG - posted 09:13, Thursday 15 May 2014 (11913)
Installation Meeting Minutes
8:15-8:30

Fred, Richard, Cyrus, Filiberto, Aaron, Bubba, Gerardo, Jeff B, Bubba, Travis, Hugh, Mitchell, Justin, Mike, Thomas, Jeff K, Fabrice, Alexa, Steban, Robert, Jamie, etc.


•	SRM alignment on HAM5 - (Jeff B/Jason)
•	TCS tables work continues. – (David, Thomas)
•	Getting things ready to transport the OFI - (Gerardo)
• 	Craning activity in LVEA / Moving clearoom from west bay -(Apollo)
• 	ICS rack inventory in LVEA – (Richard/Filiberto)
•	Commissioning work continues (Commissioners)
•	Testing and assembly operations continue in Staging building –(Jim/Hugh/Scott)
•	Guardian work in progress -(Jamie)


        LVEA is Laser SAFE