Reports until 09:11, Friday 16 May 2014
LHO General
patrick.thomas@LIGO.ORG - posted 09:11, Friday 16 May 2014 (11935)
Installation meeting minutes
SRM
Jason setting up for pitch measurements
Betsy running transfer functions
Jeff B. wants to connect the wiring for the bottom two stages (needs to wait for transfer function measurements to finish)

HAM4
Last TCS components to be installed: ISI probably ready for balancing next week
Betsy installing baffles

TCS
No work on X or Y CO2 tables, HWS work only: No need for laser hazard

ACB
Ready to start balancing and suspending
Photodiodes need to be tested

Staging building
Jim W. finishing testing on Unit 2

Apollo
Bubba machining parts for TCS


Unifirst will be delivering on Thursday for the next couple of weeks
Jamie and Robert scheduled for weekend work
Rai W. will be here next week to take acoustic measurements of the beam tube
Peter K. is working on ISS in the H2 PSL laser enclosure
Chris to move 3 IFO PCAL parts from the LSB, VPW and woodshop to mid X and 3 IFO PCAL parts from the LSB to mid Y