Installation Meeting Minutes
Janna Levin visiting
Work Permits
SRM: osem adjustments, TFs yesterday, need to review TFs before handing over to OFI
OFI: Staged by ham5
Baffles staged at HAM5
HAM5 SEI: Balancing a few days out (to install rest of payload)
HAM4 SEI: running TFs, HEPI locked (unlock for measurements later), may install doors if SEI happy
HAM6: start QPD Sleds, enter next Wed
ACB: swap out spacer
CPB: discussing logistics of this work
ESD investigations continue (comparing with L1) & thinking of plan
TCS: table work on Y table and Hartman table continues
Peter/Oliver in H2 Laser Enclosure