Reports until 16:43, Friday 12 August 2011
H2 INS
michael.rodruck@LIGO.ORG - posted 16:43, Friday 12 August 2011 (1210)
H2 PSL installation

Crew finished painting the diode and chiller rooms today. They also cut out 4 panels into the LVEA plenum for supply air. HVAC guys did not show up today but they are due to show up on Monday. Feedthru penetrations will be cut into place on Monday.

Images attached to this report