Reports until 10:33, Wednesday 28 May 2014
H1 General
andres.ramirez@LIGO.ORG - posted 10:33, Wednesday 28 May 2014 (12113)
Installation Meeting Minutes
Installation Meeting Minutes 

8:15-8:40

Fred, Richard, Aaron, Gerardo, Jeff B, Vern, Bubba, Travis, Hugh, Mitchell, Mike, Arnaud, Thomas, Daniel, David, Corey, etc.


•	Went over Work Permits
•	Work on HAM5 ISI (table balancing) – Hugh
•	BK hammering test on SR3/SRM  suspensions (HAM5) – Arnaud
•	TCS work continues - David
•	Sled getting ready to be moved to HAM6 – Dan/Corey
•	Quad  upper structure work in LVEA (West Bay) – Travis/Betsy
•	ESD driver work at End Y – Richard/Filiberto
•	Staging building activities ongoing – Mitchell/Scott

LVEA is Laser SAFE