Reports until 16:16, Thursday 29 May 2014
LHO General
patrick.thomas@LIGO.ORG - posted 16:16, Thursday 29 May 2014 (12135)
Ops summary
doors being craned for HAM5 and rigged such that closing the gate valve is not required

08:40 Kyle to start pump for RGA on BSC8 (WP 4647)
08:46 Aaron and Filiberto to end Y to fix short in WFS cables
08:47 Jeff B. to HAM5 to take PET swipe
09:07 Hugh to HAM5 to move equipment out of the way for door installation
09:08 Arnaud to HAM5 to take hammer measurements
09:22 Richard to end Y to drop components off for Aaron and Filiberto
09:30 Travis to LVEA test stand area to retrieve documents
10:05 Praxair driver approximately 15 minutes away
10:31 Luis Z. to end Y to install grounding wrist strap connectors on the electronics racks
10:50 Jeff B. and Andres done at HAM5
11:27 Corey to LVEA to put away equipment
12:13 Praxair truck leaving
13:11 Jodi, Travis and Betsy to the LVEA west bay
13:22 Kingsoft water to take water samples
13:27 Hugh to LVEA test stand to work on sub-assemblies for 3rd IFO ISIs
15:21 Keita to end Y to work on WFS
15:48 The septum has been installed between HAM5 and HAM6. The doors are tacked on HAM5. Sheila is transitioning the LVEA to laser hazard.