The idea is to wrap up commissioning by Saturday night. The ring heater stress test can proceed on Sunday. The vent can start Monday.
-
IMC/PRCL adjustment: Prepare to move MC2: 1.95 mm towards HAM1 (IMC needs to get shorter).
-
EY ESD fix: No in-vacuum work planned. Do we need to discharge?
-
Conflat for mirror discharging: Need to refit in EX.
-
Camera ports: Put new viewports in (need ECR, Corey).
-
EY QPD centering: nothing to do.
-
EX QPD centering: Friday morning (Keita, Daniel)
-
POP beam path beamsplitter: procedure by Lisa (Thursday)
POP QPD sled was centered in the past (Keita lead)
-
Change mode of ALS/POP periscope in HAM1: Tighten screws (next HAM1 vent)
-
Are all in-vacuum picos working? yes.
-
Test photodetector pods for leaking? No.
-
Alignment fiducials:
Mark IMC REFL on the wall, on ISCT (Sheila, Friday)
REFL beam on WFS (write down TT bias)
REFL beam parking position(?)
Oplev readbacks
-
AS port alignment: still need procedure (Lisa)
-
TCS ring heater test: Sunday
-
EY ALS WFS: Saturday
-
Interferometer REFL beam dump?
-
IMC trans beam clipping? no