Reports until 15:46, Friday 30 May 2014
H1 SEI (INS, SUS)
hugh.radkins@LIGO.ORG - posted 15:46, Friday 30 May 2014 - last comment - 11:59, Tuesday 03 June 2014(12146)
WHAM5 & most of HAM6 In Air Cables Reattached & secured
When the septum was removed, the cabling between HAMs 5 & 6 were disconnected so the crew could deal with all the bolts.  I asked FClara to reconnect the cables to the WHAM6 NW feedthru, SUS & ISC I think.  I'm not familiar enough to distinguish these so I left those to him.  When they are sorted out I will complete the cable/feedthru protecting.
Meanwhile, HAM5 ISI sensors are live, don't disconnect any cabling, you'll have to cut zip ties to do so.
Comments related to this report
filiberto.clara@LIGO.ORG - 10:29, Monday 02 June 2014 (12171)
Installed SUS and ISC cabling to D3 flange of HAM6 (NW corner).

Flange    Cable           Description
D3-1C1    H1:SUS_HAM6-10  OMC TOP
D3-1C2    H1:SUS_HAM6-11  OMC Right/Side

D3-2C1    H1:ISC_HAM6-265 ASC_AS_A (WFS)
D3-2C2    H1:ISC_HAM6-266 ASC_AS_B (WFS)

Document D1300122, internal in-vacuum cabling calls out for cable ISC-265 and ISC-266 to be connected to flange D5-3C1 and D5-3C2. Document should be updated.


Filiberto Clara
hugh.radkins@LIGO.ORG - 11:59, Tuesday 03 June 2014 (12187)
HAM6 NW Cables stress relieved and E-FeedThrus protected.