justin.bergman@LIGO.ORG - posted 10:22, Monday 02 June 2014 (12170)
morning meeting

LVEA transitioned to laser SAFE

Teams taking fiducial measurements (ITMs/ETMs/OpLevs)

Ready to vent all three corner station volumes after lunch

Good results from Thomas measurements on the stability of RH over the weekend

HAM4/5 doors and HAM6 septum in place

HAM6 SLED ready to install, on hold for now

need visual inspect on HAM6 cabling lengths

Apollo restoring beer garden cleanroom---coupling with BSC1/3

installation of TCS table stops on hold

need to lock HEPI for BSC1/3 due to potential contact with HEPI crossbeams

need to protect TCS mirrors during in chamber work