ITM deinstall status

Yesterday, the BSC installation arm was put on the BSC3 door.  The annulus plumbing and the cable trays prevented the flange stiffener to be attached in the correct spot, so it was rotated 1 flange-hole down.  The arm is in the appropriate place on the flange, however.  The 5-axis lift table and QUAD elevator were then mounted on the arm.

 

This morning, Margot and Danny took swipe samples of some of the BSC3 chamber surfaces and then cleaned the floors.  Jim locked the ISI (see his entry).  Travis and I rearranged the furniture such that we can work efficiently and then plumbed in the electrical to the elevator in prep for starting deinstall this afternoon.