Morning Installation Meeting Minutes
Meeting Minutes:
ITMx--putting itmx back together and back in
ITMy--start disassembling
Mostly working in beer garden today
Deciding best way to use installation arm
BSC3 SEI investigations by Jim probably today
Discussion about temperature measurements
HAM6: finishing out
HAM5/6 annulus testing (Apollo/Kyle) probably Mon
EY spool cleanroom disassembly-->Apollo disassembling/assembling cleanrooms
H2 ISS work continues (Peter K)
Mitch: most likely switching from CPB to SEI Staging (did lots of cutting/drilling yesterday)
Filiberto & crew continue elec work on BSC SEI...could move to HAM SEI later
Morning (40 at 11am) & Afternoon (dozen at 3) tours by Dale
visitors next Gary & guillermo