LHO General
patrick.thomas@LIGO.ORG - posted 10:10, Tuesday 10 June 2014 (12278)
morning meeting notes
HAM6 is fully payloaded. Hugh will unlock and balance the ISI and inspect the cabling.
Keita and Corey are done with HAM6 in chamber work.

ITMY is ready to come out.
ITMX will be installed today.

A first cleaning has been done in the spool area at GV7.
Kyle will install a vacuum pump.
Thomas and Jason will remove the optical lever components. Apollo will remove the optical lever piers.
Apollo will break bolts and remove the annulus piping.
A second cleaning will be done.
The spool will probably be removed tomorrow.

The H1 PSL laser diodes are reaching the end of their life.

Filiberto will be working on SUS watchdog cabling at end Y in addition to the ongoing AA/AI chassis work.

Jeff K. will add damping software infrastructure for the BS.

The storage container for the 3IFO BSC1 needs to be craned into its LTS location. The 3IFO HAM4 and 5 ISIs need to be moved from their shipping containers to their LTS containers.

GV11 and GV18 will be closed for Y2 accumulation pressure measurements.

Temporary plugs will be put in the annulus ports on the HAM5 and 6 door flanges to allow leak checking of the septum between the chambers.

Cyrus is doing maintenance on the CDS switches.